Total Cost of Construction 22 Marla House

The average cost of constructing a 22 Marla house varies based on region, design, materials, and labor availability. It includes grey structure construction, interior finishing, services, and internalization. Additional costs include excavating, foundation, plumbing, and electricity. The cost of high-quality materials also impacts the total expenditure.

Let’s now work out the approximate covered areas in square feet per floor that we would see in a 22 Marla house and based on the rates given in the table we will work out all the associated costs.

BASEMENT FLOOR COVERED AREA3000
GROUND FLOOR COVERED AREA3200
FIRST FLOOR COVERED AREA3000
SECOND FLOOR COVERED AREA400
BASEMENT GREY STRUCTURE BUDGET/ SQ FT.4000
GREY STRUCTURE BUDGET HOUSE OTHER/ SQ FT.2900
BASEMENT GREY STRUCTURE GOOD/ SQ FT.4500
GREY STRUCTURE GOOD HOUSE OTHER/ SQ FT.3200
BUDGET FINISHES/ SQ FT.4000
A QUALITY FINISHES/ SQ FT.5000
PREMIUM QUALITY FINISHES6000

Let’s calculate the single Storey house cost for budget, A quality & premium quality house.

SINGLE STOREY BUDGET HOUSEGREY STRUCTUREFINISHING
 GROUND FLOOR               9,280,000                     12,800,000
 TOTAL               9,280,000                     12,800,000
The total cost for budget single Storey house is 22,080,000
SINGLE STOREY A QUALITY HOUSEGREY STRUCTUREFINISHING
GROUND FLOOR             10,240,00016,000,000
 TOTAL             10,240,00016,000,000
The total cost for A Quality single Storey house is 26,240,000
SINGLE STOREY PREMIUM QUALITY HOUSEGREY STRUCTUREFINISHING
GROUND FLOOR             10,240,000                     19,200,000
 TOTAL             10,240,000                     19,200,000
The total cost for Premium Quality single Storey house is 29,440,000.

NON BASEMENT DOUBLE STOREY BUDGET HOUSE

NON BASEMENT DOUBLE STOREY BUDGET HOUSEGREY STRUCTUREFINISHING
GROUND FLOOR               9,280,000                     12,800,000
FIRST FLOOR               8,700,000                     12,000,000
TOTAL             17,980,000                     24,800,000
The total cost for budget NON-BASEMENT DOUBLE Storey house is 42,780,000.
NON-BASEMENT DOUBLE STOREY A QUALITY HOUSEGREY STRUCTUREFINISHING
GROUND FLOOR             10,240,00016,000,000
FIRST FLOOR 9,600,00015,000,000
TOTAL 19,840,00031,000,000
The total cost for A Quality NON-BASEMENT DOUBLE Storey house is 50,840.000.
NON-BASEMENT DOUBLE STOREY PREMIUM HOUSEGREY STRUCTUREFINISHING
GROUND FLOOR 10,240,000 19,200,000
FIRST FLOOR 9,600,000 18,000,000
TOTAL 19,840,000 37,200,000
The total cost for Premium Quality NON-BASEMENT DOUBLE Storey house is 57,040,000.

BASEMENT DOUBLE STOREY BUDGET HOUSE

BASEMENT DOUBLE STOREY BUDGET HOUSEGREY STRUCTUREFINISHING
BASEMENT FLOOR 12,000,00012,000,000
GROUND FLOOR 9,280,00012,800,000
TOTAL 21,280,00024,800,000
The total cost for budget BASEMENT DOUBLE STOREY house is 46,080,000.
BASEMENT DOUBLE STOREY A QUALITY HOUSEGREY STRUCTUREFINISHING
BASEMENT FLOOR 13,500,00015,000,000
GROUND FLOOR 10,240,00016,000,000
TOTAL 23,740,00031,000,000
The total cost for A Quality BASEMENT DOUBLE STOREY house is 54,740,000.
BASEMENT DOUBLE STOREY PREMIUM HOUSEGREY STRUCTUREFINISHING
BASEMENT FLOOR 13,500,00018,000,000
GROUND FLOOR 10,240,00019,200,000
TOTAL 23,740,00037,200,000
The total cost for Premium Quality BASEMENT DOUBLE STOREY house is 60,940,000.

BASEMENT TRIPLE STOREY BUDGET HOUSE

BASEMENT TRIPLE STOREY BUDGET HOUSEGREY STRUCTUREFINISHING
BASEMENT FLOOR 12,000,00012,000,000
GROUND FLOOR 9,280,00012,800,000
FIRST FLOOR 8,700,00012,000,000
 TOTAL 29,980,00036,800,000
The total cost for budget BASEMENT TRIPLE STOREY house is 66,780,000.
BASEMENT TRIPLE STOREY A QUALITY HOUSEGREY STRUCTUREFINISHING
BASEMENT FLOOR 13,500,00015,000,000
GROUND FLOOR 10,240,00016,000,000
FIRST FLOOR 9,600,00015,000,000
TOTAL 33,340,00046,000,000
The total cost for A Quality BASEMENT TRIPLE STOREY house is 79,340,000.
BASEMENT TRIPLE STOREY PREMIUM QUALITY HOUSEGREY STRUCTUREFINISHING
BASEMENT FLOOR 13,500,00018,000,000
GROUND FLOOR 9,600,00018,000,000
FIRST FLOOR 33,340,00055,200,000
TOTAL 33,340,00055,200,000
The total cost for Premium Quality BASEMENT TRPLE STOREY house is 88,540,000.

BASEMENT TRIPLE STOREY BUDGET HOUSE WITH MUMTY

BASEMENT TRIPLE STOREY BUDGET HOUSE WITH MUMTYGREY STRUCTUREFINISHING
BASEMENT FLOOR 12,000,00012,000,000
GROUND FLOOR 9,280,00012,800,000
 FIRST FLOOR 8,700,00012,000,000
SECOND FLOOR 1,160,0001,600,000
TOTAL 31,140,00038,400,000
The total cost for budget BASEMENT TRIPLE STOREY house with mumty is 69,540,000.
BASEMENT TRIPLE STOREY A QUALITY HOUSE WITH MUMTYGREY STRUCTUREFINISHING
 BASEMENT FLOOR 13,500,00015,000,000
GROUND FLOOR 10,240,00016,000,000
 FIRST FLOOR 9,600,00015,000,000
 SECOND FLOOR 1,280,0002,000,000
TOTAL 34,620,00048,000,000
The total cost for A Quality BASEMENT TRIPLE STOREY house with mumty is 82,620,000.
BASEMENT TRIPLE STOREY PREMIUM HOUSE WITH MUMTYGREY STRUCTUREFINISHING
BASEMENT FLOOR 13,500,00018,000,000
GROUND FLOOR 10,240,00019,200,000
FIRST FLOOR 9,600,00018,000,000
SECOND FLOOR 1,280,0002,400,000
TOTAL 34,620,00057,600,000
The total cost for Premium BASEMENT TRIPLE STOREY house with mumty is 92,220,000.

In conclusion, constructing a 22-marla house is a significant investment that requires careful planning and budgeting. From the grey structure to the final finishes, each phase of construction impacts the overall cost. By choosing quality materials, efficient designs, and experienced labor, you can balance cost-effectiveness with durability and aesthetics. It’s essential to account for market fluctuations, unforeseen expenses, and evolving design preferences during the process. A well-planned approach not only ensures timely completion but also enhances the value of your property. Whether building for personal use or investment, meticulous planning will help you achieve your dream home within budget.